Annular heating furnace mechanical equipment installation

Installation of Circular Heating Furnace Mechanical Equipment Circular heating furnace is an indispensable equipment for smelting and heat treatment in some large machinery factories and chemical corporations. Its installation is related to the efficient operation and quality of the products in s......

Installation of Circular Heating Furnace Mechanical Equipment

Circular heating furnace is an indispensable equipment for smelting and heat treatment in some large machinery factories and chemical corporations. Its installation is related to the efficient operation and quality of the products in such factories and corporations, so the installation process and procedures should be strictly followed.

To install a circular heating furnace safely and efficiently, following steps must be taken before beginning installation:

1. Preparation:

Maximize the nearby space and clear obstacles during installation;

Check the location and validate its stability;

Layout the installation ground, which should be flat and level;

Check necessary tools and their availability;

Layout the parts and pieces according to the furnace plan.

2. Inspect and assemble the furnace:

Check if the components are complete and have any visible damages;

Observe the component structure, such as liner structure and insulating layer;

Assemble the liner, insulation layer, heating elements and thermostats appropriately;

Fill in the furnace and ensure that it is sealed.

3. Install the furnace:

Validate the installation position, dig the pit of appropriate size, and make foundations;

Fix the pedestal and keep the platform of the furnace horizontal;

Fix the crusher round the furnace, refractory insulation layer, furnace cover and the flue;

Put the heating element and other components into the furnace, turn on the power to operate a test run;

Adjust the power input according to the temperature rising rate of the furnace, and keep the furnace reaching the specified temperature as soon as possible;

Check if the furnace is installed safely and if there are any malfunction.

4. After installation

Clean out the installation site;

Inspect if the installations meet the design requirement;

Make proofread records and adopt necessary preventive measure.

By strictly following the above steps and procedures, it will be possible to install a circular heating furnace machine safely and efficiently. As a professional machinery manufacturer, we has specialized personnel equipped with professional skills and experiences to help our customers in installation of circular heating furnace.