Rules for Operation of JF4002 Internal Casting Jacketed Pan Mill
JF4002 internal casting jacketed pan mill is an essential equipment in various industries and industries. Proper operation and maintenance of this equipment is the precondition for maximizing its performance and prolonging its service life. This article will introduce the rules for operation of JF4002 internal casting jacketed pan mill in detail.
1. Preparation before starting
1.1 Before the starting operation of JF4002 internal casting jacketed pan mill, the operator should check whether the transmission parts are in good lubrication condition and whether the operation is normal; pay attention to check whether the spindle decelerator is tightly connected.
1.2 If there is any abnormality in the above checking, related maintenance and adjustment should be carried out before starting.
1.3 Check that the speed change of the spindle decelerator is correct.
1.4 It is necessary to check whether the tools are complete, whether their intensity is in accordance with the design requirements and whether they have obvious wear and tear. If any of the above conditions exist, the operator should adjust or replace them immediately.
1.5 Check that the workplace and the environment are clean, and clean up the sundries in the mill.
1.6 The operator should check whether the power switch is set in the off position, and plug the power plug into the energy socket.
1.7 It is necessary to check whether the fastening screws at all parts of the JF4002 internal casting jacketed pan mill are safe.
2. Starting process
2.1 Turn on the power switch and adjust the spindle decelerator speed to determine the spindle decelerator speed correctly.
2.2 Start the JF4002 internal casting jacketed pan mill gradually, check the operation of the mill and make sure that the speed is appropriate.
3. Operation process
3.1 After turning on the power switch, the operator should check whether the voltage and amperage are within the standard range.
3.2 When feeding material, the feeding speed should be increased gradually to avoid the blocking of material.
3.3 The operator should pay attention to always check the current load, and make sure that the motor current is not too high.
3.4 Pay attention to observe the thermal anomaly of the motor, and immediately stop the machine when it is not normal.
3.5 When the machine is working, check the vibration degree of the spindle regularly. If the vibration is obviously abnormal, stop the machine immediately to eliminate the fault.
3.6 Pay attention to observe the appearance of the internal casting jacketed pan mill. If there is any abnormality, stop the machine immediately and submit the report to the corresponding personnel.
4. Shut down process
4.1 During the work, if a sudden electric shock or something broken appears, please turn off the power switch immediately and stop the machine at once.
4.2 The operator should turn off the power switch after completing the production task.
4.3 Cut off the power supply and unplug the power plug from the power socket.
5. Maintenance
5.1 After the work is finished, the operator should clean the inside and outside of the internal casting jacketed pan mill in time, and wipe off the oil and dirt on the surface of the bearing.
5.2 Regularly check the connection of the spindle decelerator and all parts of the equipment and check whether the fastening screws are loose. If any abnormality is found, it must be adjusted and tightened in time.
5.3 Timely check and replenish the fuel tank of the lubrication device.
These are the rules for operation of JF4002 internal casting jacketed pan mill. The correct operation of the equipment is the guarantee of its efficient and continuous work, so the operator should pay attention to the operation process according to the relevant rules. Only when the equipment operation is correct can we get satisfactory results and enjoy the convenience brought by the equipment.